For updated information about ongoing construction, visit the maps/traffic impacts section.
Eastside Pipeline
Completed
Project Description: Approximately 9,500 linear feet (1.8 miles) of 66” pipeline that will begin on Chappell Road and the North Diversion Channel, head east on Singer Boulevard to Jefferson Road, head south in the Jefferson right-of-way, then turn north within the south I-25 right-of-way to a point east of PF Chang's restaurant, then tunnel east under I-25 to Osuna Road, continue east on Osuna past San Mateo Boulevard, then stop at the western edge of the Arroyo del Oso Golf Course (just west of San Pedro).
Consultant: DMJM
Contractor: RMCI, Inc.
Start Date: July 5, 2005
Construction End Date (Estimated): April 2007
Major Streets Affected: Chappell, Singer, Jefferson, Osuna, San Pedro
Coronado Pipeline
Completed
Project Description: Approximately 18,000 linear feet (3.4 miles) of 30” pipeline that will begin on Academy Road, proceed east on Academy to McKinney Drove, then turn north on McKinney to Forest Hills Drive, then west on Forest Hills to just east of the I-25 frontage road, then north to Del Rey Avenue, then east on Del Rey to San Pedro Drive, then north on San Pedro to Palomas Ave., then east on Palomas to the Coronado Reservoir.
Consultant: DMJM
Contractor: RMCI, Inc.
Construction Start Date: July 2006
Construction End Date: August 2007
Major Streets Affected: Academy, Forest Hills Drive, McKinney Drive, Louisiana, Osuna
Burton Pipeline
Currently under construction
Project Description: 15,200 linear feet (2.88 miles) of 36” pipeline that will begin at the Burton Reservoir and end at Alvarado Drive/Roma Avenue.
Consultant: ASCG
Contractor: ERS Constructors
Construction Start Date: (Estimated) June 2007
Construction End Date: (Estimated) Spring 2008
Major Streets Affected: Wellesley Drive, Santa Clara, Amherst, Pershing, Hermosa, Marquette, Roma, Alvarado
Charles Wells Pipeline
Completed
Project Description: 18,000 linear feet (3.4 miles) of 36”, 42” and 54” pipeline that will begin where the Burton Pipeline left off (Alvarado Drive/Roma Avenue) and end at San Pedro Drive/Arvilla Avenue.
Consultant: ASCG
Contractor: ERS Constructors
Construction Start Date: Fall 2006
Construction End Date: October 2007
Major Streets Affected: Alvarado, Haines, San Pedro, Phoenix, Chama, Prospect.
Leyendecker Pipeline
Completed
Project Description: 11,200 linear feet (2.1 miles) of 42", 54" and 60" pipeline that will begin where Charles Wells Pipeline Phase 2 left off (San Pedro Drive/Arvilla Avenue) and end at San Pedro Drive/Osuna Road.
Consultant: ASCG
Contractor: Shumate/ERS
Construction Start Date: February 2006
Construction End Date: August 2006
Major Streets Affected: San Pedro, Osuna, Hendrix, Andrew
West Side Pipeline
Completed
Atrisco Road & Ladera Drive to Sequoia/Alamogordo Drive
Project description: Approximately 2,265 linear feet (nearly 1/2 mile) of 36” pipeline and 2,561 feet (nearly 1/2 mile) of 60” pipeline that will begin at the intersection of Atrisco & Ladera roads, continue south on Atrisco to Sequoia Road, turn east at Sequoia and continue across Coors Blvd. to west of Alamogordo Drive. This pipeline will connect with the Rio Grande Crossing Pipeline.
Consultant: BHI
Contractor: AUI, Inc.
Start Date: March 2005
Construction End Date: May 2006
Major Streets Affected: Ladera, Coors, Sequoia, Atrisco, St. Joseph's
Rio Grande Crossing Pipeline
Completed
Project description: Approximately one-mile project includes about 1,000 linear feet of 60” pipeline and 4,000 linear feet of 54” welded steel pipe that begins at Sequoia Road west of Alamogordo Drive, continues east on Sequoia, down the west bluff, and crosses the Rio Grande and its Bosque to the west end of Campbell Road.
Consultant: BHI
Contractor: AUI, Inc.
Construction Start Date: August 2004
Construction End Date: July 2006
Major Streets Affected: Sequoia, Alamogordo, Campbell
East Valley Pipeline
Completed
Second Street to Water Treatment Plant
Project description: Approximately 15,150 linear feet (2.86 miles) of 72” pipeline that starts adjacent to the Alameda Drain at Second Street south of Candelaria Road, extends north across Second Street, then east on Candelaria to Edith Boulevard, then north on Edith to the Alameda Lateral, northeast along Montano Road, than east on Montano to Renaissance Boulevard. The pipeline stops at the south tie-in point of the discharge line for the surface water treatment plant.
Consultant: BHI
Contractor: AUI, Inc.
Start Date: June 2005
Construction End Date: May 2007
Streets Affected: Candelaria, 2nd Street, Edith, Montano, Industrial, Renaissance.
West Valley Pipeline
Completed
Project description: 3,690 linear feet (about 2/3 of a mile) of 60" pipeline and 10,390 linear feet (nearly 2 miles) of 66" pipeline that begins at the west end of Campbell Road, adjacent to the Rio Grande Bosque, and connects to the River Crossing project, continuing east in Campbell Road, crossing Rio Grande Blvd. to the Griegos Lateral, south along the Griegos Lateral, crossing Matthew Avenue to the Alameda Drain, then running east along the Alameda Drain to 2nd Street to tie into the East Valley project. This project will result in an improved pedestrian/bike trail in the Bosque.
Consultant: BHI
Contractor: RMCI, Inc.
Construction Estimated Start Date: November 2005
Construction End Date: September 2007
Major Streets Affected: Campbell, Rio Grande, 12th Street at the Alameda Drain, 4th Street at the Alameda Drain, Matthew.
College Pipeline Middle Segment
Completed
Project description: 13,600 linear feet (2.5 miles) of 54” and 60” pipeline that begins on 98th Street, extends east on Old Ouray Road, and winds through the southern edge of Ladera Golf Course to connect to the Westside pipeline at Atrisco Road.
Consultant: HDR
Contractor: RMCI, Inc.
Construction Start Date: April 2005
Construction End Date: April 2006
Major Streets Affected: 98th Street, Unser, Old Ouray, Ouray, Ladera, Sequoia.
Don Pipeline South Segment
Completed
Project description: 23,000 linear feet (4.3 miles) of 36”, 42” and 48” pipeline that begins at the College Reservoir, headseast on Tierra Pintada St., then on 98th Street, under I-40, to Bluewater, then to 110th Street, connecting to the Don Reservoir.
Consultant: HDR
Contractor: Shumate/ERS Constructors
Construction Start Date: March 2005
Construction End Date: November 2005
Major Streets Affected: 98th, Arroyo Vista, Bluewater, Central, 106th Street, 110th Street
Volcano Pipeline North Segment
Near completion
Project description: 9,200 linear feet (1.8 miles) of 36" pipeline that begins at Atrisco and Sequoia and extends north on Unser to Montano.
Consultant: HDR
Contractor: A.S. Horner
Construction Start Date: June 2006
Construction End Date: November 2007
Major Streets Affected: Atrisco, Unser, Western Trail, Dellyne, Montano.
Raw Water Pipeline #1 from Diversion Dam
Completed
Project description: 72" diameter steel pipe and will extend for approximately 17,500 linear feet (3.3 miles) from the Rio Grande River to Paseo Del Norte/North Diversion Channel.
Consultant: Boyle Engineering
Contractor: Bradbury & Stamm/SJ Louis
Construction Start Date: November 2005
Construction End Date: June 2007
Major Streets Affected: Rio Grande, Edith, Fourth Street NW, BNSF Mainline Railroad Track, Second Street NW, Paseo del Norte.
Raw Water Pipeline #2 to Water Treatment Plant
Completed
Project description: 72" diameter steel pipe and will extend for approximately 14,600 linear feet (2.76 miles) from Paseo Del Norte/North Diversion Channel to the new Water Treatment Plant near Chappell Road.
Consultant: Boyle Engineering
Contractor: AUI, Inc
Construction Start Date: June 2006
Construction End Date: October 2007
Major Streets Affected: 2nd Street NW, Paseo del Norte, BNSF Reeves Spur, Chappell Road, Singer Blvd.
West Raw Water Pump Station
Currently under construction
Project description: Located on the northwest corner of the Bachechi Open Space, the raw water pump station will be highlighted with a 32' parapet to add architectural interest and will blend in with area homes and architecture. The pump station will be fully xeriscaped, with minimal down-lighting, and will serve as an access point to Alameda/Rio Grande Open Space. It will feature special noise-dampening features and will be remotely operated to minimize disruption to the area.
Consultant: Boyle Engineering
Contractor: RMCI, Inc.
Construction Start Date: June 2006
Construction End Date: January 2008
Major Streets Affected: Construction vehicles will access the site from the Alameda/Rio Grande Open Space, but no major roads are expected to be affected.
Raw Water Diversion Dam
Completed
Project Description: Obermeyer Inflatable Dam rising 3 to 3.5 feet above Rio Grande at operating height, located 1,500 feet south of Alameda Blvd. West half of Dam will be constructed first; east half will be constructed second. Includes an intake/fish screen to keep fish out of pump station and a fish passage to provide a pathway around the dam for fish.
Consultant: Boyle Engineering
Contractor: ASI
Construction Start Date: January 2005
Construction End Date (Estimated): April 2006
Major Streets Affected by Diversion Dam Include: Rio Grande, Loretta, Erwin, Polo, Lucyle, Bosque Circle
|